SEMINOLE MASONRY, LLC

OVIEDO, FL

Inspections With Violations2
Total Citations4
Total Penalties$21,290.60
Most Recent CaseJanuary 13, 2021

January 13, 2021 · Follow-up

OSHA case 345103071

5A0001 · Serious · $9,557.00

29 CFR OSH ACT of 1970 Section (5)(a)(1): The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees, in that; employees were exposed to struck-by and crush-by hazards: On or about January 11, 2021, at the jobsite located at 167 Linlake Cove, Oviedo, FL, an employee was exposed to struck-by and crush-by hazards, when walking in the path of travel of a JCB-509-42 powered industrial truck that was transporting a suspended precast concrete wall. IN THE ALTERNATIVE: 29 CFR 1926.602(c)(1)(vi): Industrial truck(s) in use did not meet the applicable requirements of design, construction, stability, inspection, testing, maintenance, and operation, as defined in American National Standards Institute B56.1-1969, Safety Standards for Powered Industrial Trucks: On or about January 11, 2021, at the jobsite located at 167 Linlake Cove, Oviedo, FL, an employee was exposed to struck-by and crush-by hazards, when walking in the path of travel of a JCB-509-42 powered industrial truck that was transporting a suspended precast concrete wall.

Final order entered May 25, 2021.

March 7, 2017 · Referral

OSHA case 342158003

29 CFR 1926.451(a)(1) · Serious · $5,866.80

29 CFR 1926.451(a)(1): Scaffold(s) and scaffold(s) component(s) were not capable of supporting, without failure, its own weight and at least four times the maximum intended load applied or transmitted to it: a. On or about 02/28/2017, at the trash compactor enclosure - employees loading cement blocks to a veneer jack scaffold fell 4 feet to the ground after the scaffold collapsed. The scaffold was erected on soft ground and mud sills were not used. The scaffold was loaded with approximately 70 cement blocks and 5 employees.

Final order entered August 21, 2017.

29 CFR 1926.451(c)(2) · Serious · $5,866.80

29 CFR 1926.451(c)(2): Supported scaffold poles, legs, posts, frames, and uprights did not bear on base plates and mud sills or other adequate firm foundation: a. On or about 02/28/2017, at trash compactor enclosure - employees loading cement blocks to a veneer jack scaffold fell 4 feet to the ground after the scaffold collapse, the scaffold was erected on soft ground and mud sills were not used.

Final order entered August 21, 2017.

29 CFR 1926.454(b)(3) · Other-Than-Serious · $0.00

29 CFR 1926.454(b)(3): The employer did not ensure employee training was completed related to the design criteria, maximum intended load-carrying capacity and intended use of the scaffold. a. On or about 02/28/2017, at the trash compactor enclosure - employees were not trained on the capacity veneer jack scaffold. The scaffold collapse while loading cement blocks and employees fell 4 feet to the ground after, the scaffold was erected on soft ground and mud sills were not used.

Final order entered August 21, 2017.

Potential Matches

Other locations on file under the exact same company name. OSHA News does not combine these with the facility above - a shared name is not proof of a shared company, so click through to judge for yourself whether a listing below is really the same business.

CityStateInspectionsMost Recent
CitySANFORD StateFL Inspections1 Most RecentFeb 20, 2025
CityKISSIMMEE StateFL Inspections1 Most RecentAug 24, 2020
CitySAINT CLOUD StateFL Inspections1 Most RecentApr 25, 2018
CityORLANDO StateFL Inspections1 Most RecentJul 9, 2015